Teffont Substation

19 Oct 2026

Author Dolman

Category

We’ve been involved with the arrangement of a new SSE Substation, to power Teffont Hotel and the wider village as the existing substation is very old and now significantly undersized.

It’s amazing the amount of legislation that’s been touched on: –

  • Full Planning Permission & Listed Building Consent granted for the demolition of an existing building, for the siting of the new substation, in the curtilage of Clients Listed building.
  • Section 211 Notice for the removal of a tree in a Conservation Area.
  • Highways license for drilling under the road.
  • Environmental Agency exemption permit for drilling under a chalk stream.

Progress is being made and it’ll be a relief for all parties once SSE are onsite.