Medical Wire

01 Mar 2022

Author Dolman

Category

Works are progressing well with the wall cladding 60% complete, the Ground Floor Office floor has been cast; the Production/Warehouse Area floor is to be cast next week. Windows and doors and internal partitioning will follow, and external yard areas will re-commence. PV Solar panels are upon the roof along with the fall arrest system.

A summer completion is expected.