Cross Manufacturing, Office and Warehouse building

01 Mar 2020

Author Dolman

Category

Works are progressing well at Hopton Industrial Estate for this 1135m2 project, the cladding is complete, and windows and doors have been installed.  Internally the partitions and ceilings are in place and second fix is underway, completion is due early April with Client fit out planned for April & May.